Chairman CDA Visits Islamabad Expressway East Project, Reviews latest Progress and Directs Timely Completion of the project, ensuring quality and standards
Islamabad, October 22, 2026: Chairman Capital Development Authority (CDA) Sohail Ashraf visited the Islamabad Expressway Service Road East Project and reviewed the latest progress and quality and standard of ongoing development works. He directed the concerned officers to ensure timely completion of the project in accordance with approved designs while maintaining the highest construction quality standards.
During the visit, the Chairman CDA was also briefed on the ongoing enforcement operation against illegal construction, unauthorized commercial activities and violations of building control regulations along Islamabad Expressway East.
So far, 58 buildings have been sealed, while 124 structures between Sohan and Khanna Pul have been identified for demolition. A total of 377 structures, including 281 commercial buildings, have been identified for enforcement action.
The enforcement operation has resulted in the recovery of Rs. 250,590,157 (approximately Rs. 250.59 million), while approximately Rs. 3 billion remains recoverable under applicable regulations.
Chairman CDA Sohail Ashraf directed the concerned formations to ensure strict and uniform implementation of building control regulations, land use rules and mandatory fire safety requirements.
He further directed that development projects be completed within the stipulated timelines without compromising on quality or construction standards. He reaffirmed CDA's commitment to accelerating development, improving infrastructure and transforming Islamabad into a modern, beautiful and well planned capital.
During the visit, the Chairman CDA was also briefed on the ongoing enforcement operation against illegal construction, unauthorized commercial activities and violations of building control regulations along Islamabad Expressway East.
So far, 58 buildings have been sealed, while 124 structures between Sohan and Khanna Pul have been identified for demolition. A total of 377 structures, including 281 commercial buildings, have been identified for enforcement action.
The enforcement operation has resulted in the recovery of Rs. 250,590,157 (approximately Rs. 250.59 million), while approximately Rs. 3 billion remains recoverable under applicable regulations.
Chairman CDA Sohail Ashraf directed the concerned formations to ensure strict and uniform implementation of building control regulations, land use rules and mandatory fire safety requirements.
He further directed that development projects be completed within the stipulated timelines without compromising on quality or construction standards. He reaffirmed CDA's commitment to accelerating development, improving infrastructure and transforming Islamabad into a modern, beautiful and well planned capital.
More from the gallery
View all
12 Nov 2026
Chairman CDA Holds Open Kutcheri in Park Enclave; Directs Priority Resolution of Residents’ Issues and Improvement of Civic Facilities

11 Nov 2026
Chairman CDA and Chief Commissioner Islamabad visits Sector C-14, reviewed ongoing development activities in details

11 Nov 2026
Visit of Faculty Members and Probationary Officers of the 54th Common Training Programme of Civil Services Academy Lahore to CDA Headquarters

09 Nov 2026
Chairman CDA and Chief Commissioner Islamabad visit the Margalla Avenue N5 to M1 Extension and Sangjani Interchange project, detailed review of construction work

07 Nov 2026
After the retrieval of 1135 kanals of Government land in Sector E-12 pending for four decades, full-scale work on sector development is underway

08 Nov 2026